Analisis Produktivitas Penggunaan Alat Berat pada Pekerjaan Galian dan Timbunan Tanah (Studi Kasus: Sumedang Industrial Polis)
Keywords:
Construction Equipment, Earthwork, Operational Cost, Productivity, Project DurationAbstract
Earthwork in an industrial development requires heavy-equipment management that balances productivity, project duration, and operating cost. This study analyzes equipment productivity, fleet requirements, completion time, and operating costs for an excavator, dump trucks, and a bulldozer in the Sumedang Industrial Polis Project, and compares 120-day and 90-day execution scenarios. A quantitative technical-analysis approach was applied using primary data from cycle-time observations, operating conditions, and field observations, together with secondary data on work volume, equipment specifications, working hours, and operating costs. The excavation volume was 48,944 m³ and the corresponding loose-soil volume used in the analysis was 61,180 m³. The calculated basic productivity was 105.727 m³/hour for the excavator, 28.518 m³/hour for each dump truck, and 134.864 m³/hour for the bulldozer. The required fleet remained one excavator, three dump trucks, and one bulldozer in both scenarios. Shortening the schedule to 90 days increased the required effective excavator productivity from 63.730 to 84.972 m³/hour, which remained below the available capacity. Total operating cost decreased from IDR 3,840,081,528 to IDR 3,532,483,608, producing a saving of IDR 307,597,920 or approximately 8.01%. Therefore, with the same equipment configuration, the 90-day scenario provides a shorter execution period and a lower operating cost.
References
Daffa, M.A.D. and Zhafirah, A. (2026) “Analisis produktivitas alat berat pada pekerjaan timbunan untuk proyek infrastruktur irigasi,” Jurnal Konstruksi, 24(1), pp. 707–714. Available at: https://doi.org/10.33364/konstruksi/v.24-1.2021.
Efriansyah, M., Prihutomo, N.B. and Pramono, E. (2022) “Analisis produktivitas excavator dan dumptruck pada pekerjaan galian tanah pada proyek Jalan Tol Jakarta--Cikampek II Selatan,” Media Komunikasi Dunia Ilmu Sipil (MoDuluS), 4(1), pp. 9–15. Available at: https://doi.org/10.32585/modulus.v4i1.1823.
Hino Indonesia (2020) “Spesifikasi Hino Dutro 130 HD 7 m3.”
Kahandanie, F. and Kartika, D.M.R. (2025) “Optimalisasi produktivitas alat berat galian dan timbunan konstruksi perumahan Balikpapan,” Jurnal Multidisiplin Dehasen (MUDE), 4(2), pp. 309–318. Available at: https://doi.org/10.37676/mude.v4i2.8262.
Komatsu Indonesia (2016) “Spesifikasi bulldozer Komatsu D65E.”
Kusumo, A.T.H. et al. (2022) “Analisis pemilihan alat berat dalam pekerjaan galian dan timbunan proyek Bendungan Bener,” Equilib, 3(1), pp. 55–64.
Listyawan, A.B. et al. (2021) “Analisis produktivitas alat berat dan biaya pekerjaan pemindahan tanah pada pembangunan RSUD Pondok Aren Tangerang Selatan,” Dinamika Teknik Sipil: Majalah Ilmiah Teknik Sipil, 14(1), pp. 8–12. Available at: https://doi.org/10.23917/dts.v14i1.15272.
Novty, T. (2018) “Analisis efisiensi dump truck pada kombinasi alat berat pekerjaan galian dan timbunan tanah.”
Nuzola, M., Herni, M. and Kurniawan, S. (2023) “Produktivitas alat berat pada galian dan timbunan,” JUMATISI: Jurnal Mahasiswa Teknik Sipil, 4(1), pp. 266–271. Available at: https://doi.org/10.24127/jumatisi.v4i1.4020.
PT Daya Kobelco Construction Machinery Indonesia (2016) “Spesifikasi excavator Kobelco SK 200.”
PT Sukses Perdana Andalan (2026) “Data proyek pembangunan Sumedang Industrial Polis.”
Putri, K.S. and Soebandono, B. (2024) “Produktivitas alat berat pada pekerjaan galian dan timbunan Embung IKN Nusantara,” Bulletin of Civil Engineering, 4(2). Available at: https://doi.org/10.18196/bce.v4i2.25852.
Rafi, Y.F. and Witjaksana, B. (2023) “Productivity analysis of excavator and dump truck heavy equipment on digging and loading works flood control Afvoer Watudakon Mojokerto,” Jurnal Teknik Sipil, 23(2), pp. 205–210. Available at: https://doi.org/10.26418/jtst.v23i2.61025.
Rochmanhadi (1986) Alat-alat berat dan penggunaannya. Departemen Pekerjaan Umum.
Rostiyanti, S.F. (2002) Alat berat untuk proyek konstruksi. Rineka Cipta.
Siregar, S.Y. and Pasaribu, H.M. (2021) “Analisis produktivitas alat berat pada pekerjaan galian Gedung Pusdiklat Prasadha Jinadhammo,” Jurnal Ilmiah Teknik Sipil Agregat, 1(2), pp. 63–71. Available at: https://doi.org/10.51510/agregat.v1i2.515.
Suryadharma, H. and Wigroho, H.Y. (1998) Alat-alat berat. Cahaya Atma Pustaka.
Wardani, L.M.I. and Firmansyah, R. (2021) Work-Life Balance Para Pekerja Buruh. PT Nasya Expanding Management.
Wilopo, D. (2009) Metode konstruksi dan alat-alat berat. UI Press.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 JPNM Jurnal Pustaka Nusantara Multidisiplin

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.